DOSKOČIL, R. DOUBRAVSKÝ, K.
Original Title
Risk Analysis of Stochastic PERT Graph
Type
journal article - other
Language
English
Original Abstract
The paper deals with a time and probability analysis of stochastic graph PERT. The paper focuses on the comparison of two different approaches calculation of probability analysis and their influence on the calculation of the planning time of the project. Concretely the planning time of the project was calculated. A sample PERT network graph was examined, which comprised 18 nodes and 18 real activities and 6 fictions activities. For the purpose of the analysis, the basic characteristic times were calculated in accordance with traditional approaches related to the PERT method. For probability analysis was also calculated expected value, variance and standard deviance of the activities. For calculation of the planning time was used distribution function of standardized normal distribution. The PERT algorithm is realized by using spreadsheet in the MS Excel.
Keywords
network graph, PERT method, node criticality, mean value, probability analysis
Authors
DOSKOČIL, R.; DOUBRAVSKÝ, K.
RIV year
2013
Released
1. 7. 2013
Publisher
Akademické nakladatelství CERM
Location
Brno
ISBN
1802-8527
Periodical
TRENDY EKONOMIKY A MANAGEMENTU
Year of study
7
Number
14
State
Czech Republic
Pages from
35
Pages to
43
Pages count
9
BibTex
@article{BUT100600, author="Radek {Doskočil} and Karel {Doubravský}", title="Risk Analysis of Stochastic PERT Graph", journal="TRENDY EKONOMIKY A MANAGEMENTU", year="2013", volume="7", number="14", pages="35--43", issn="1802-8527" }