ŠTRBA, M.
Originální název
On the Problems of Testing Methodology used in Case of the Temporary Steel through Truss Footbridge Development
Typ
článek v časopise - ostatní, Jost
Jazyk
angličtina
Originální abstrakt
This paper brings some information about a performed research project in which a testing methodology was used in case of development of a new type of temporary steel truss footbridge for pedestrians and cyclists. At first, the mentioned structure was designed according European standards using finite elements method software and then the point of research was to experimentally verify the actual behaviour of the footbridge in the event of real loading. For that purpose they were firstly performed tests on selected members and details using tension and compression static force. According the obtained results it was used cyclic force for some parts as well. Finally, there was performed a test of full-scale prototype as well. In this paper there are some particular results and illustrative photos of the research presented.
Klíčová slova
Actual behaviour, joints, loading test, steel structure, temporary footbridge
Autoři
Rok RIV
2013
Vydáno
1. 12. 2013
Nakladatel
North Atlantic University Union
Místo
U.S.A.
ISSN
1998-4448
Periodikum
International Journal of Mechanics
Ročník
7
Číslo
2
Stát
Spojené státy americké
Strany od
73
Strany do
80
Strany počet
8
BibTex
@article{BUT104765, author="Michal {Štrba}", title="On the Problems of Testing Methodology used in Case of the Temporary Steel through Truss Footbridge Development", journal="International Journal of Mechanics", year="2013", volume="7", number="2", pages="73--80", issn="1998-4448" }